Typical timeline
- Week 0You submit the application and pay the fee.
- ValidationThe council checks it has everything. Missing items can cause delays.
- Consultation, usually 21 daysNeighbours are notified, a site notice may go up, and consultees respond.
- Officer assessmentA planning officer may visit, then writes a report and recommendation.
- Decision, target 8 weeksFor most householder applications, from validation. Major applications have a 13-week target.
Delegated or committee
Most householder applications are decided by officers under delegated powers. Some go to a planning committee, for example when there are many objections.
If it's taking longer
Councils may ask you to agree an extension of time, especially if amendments are needed. Keep in touch with the case officer.
Track it in your account
Your PlanningQuotes project account lets you record your submission date and see the 8-week target.
Questions
Can I start work before a decision?
No. Building before approval is at your own risk and may lead to enforcement action.
What is validation?
The council's check that your application has the required forms, drawings, fee and documents.
Can neighbours stop my application?
Neighbours can comment, but decisions are made on planning grounds, not the number of objections.
England focus. This guide covers the system in England. Wales, Scotland and Northern Ireland have their own rules and portals. Rules and fees change, so always check the Planning Portal and your council before you apply. This is general guidance, not legal advice.